Timeline

Below is a timeline of our project. We’ll try to keep it updated as we go along:

February 2018

  • First saw the house

May 2018

  • Moved in

October 2018

  • Started working with architect

November 2019

  • Submitted planning application

January 2019

  • Bat survey
  • Tree survey

March 2019

  • Planning application extended as council had missed out consulting some of our neighbours.

April 2018

  • Planning application granted

July 2019

  • Building regulations and structural drawings completed.
  • First tendering process.

October 2019

  • Secondary tendering process

December 2019

  • Builder selected

January 2020

  • Project kick off meeting with builder, plumber and electrician
  • Minor amendments to plans submitted to council
  • Part wall agreement completed
  • Updates to building regulations and structural drawings

February 2020

  • Approval for the non-material amendment to the planning application.
  • Kitchen design finalised?.
  • Garage door chosen?
  • Planned start date